6th World Congress on Tall Buildings and Urban Habitat
melbourne
2001

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

labour and materials: contracts

 

 

 

 

 

 

 

 

 

 

 

J McMullan

 


1.                 CONTRACT FORMS

 


1.1                 Forms adopted by Building Owners

There are a range of contract types which may be attractive on a particular building project.

 

Most major projects within the private sector do not employ standard form Conditions of Contract.

 

This may be due to a lack of confidence, by project lawyers, usually the Principal's lawyers, in those documents when the stakes are high.  Alternatively, however, and more likely, it seems to me that the standard form of Conditions of Contract available, to date, have simply been unsuitable on very large projects, where a substantial amount of consultant advice, including legal advice, is usually taken prior to execution of the project documents.

 

For example, most of the standard form Conditions of Contract are based on the traditional principal/contractor relationship, with a Superintendent acting in the dual agent/independent certifier role. In recent years, however, many  major projects have proceeded on the basis of a completely different project delivery system including, for example:-

 

Design and Construct

                 Warranted Maximum Price

Project Management

Construction Management

                 Turnkey

                 BOT (Build/Own/Transfer)

 

Each of these project delivery systems has been used, to my knowledge, on one or more major projects in Australia in the last five years.  The standard form Conditions of Contract have, perhaps, not kept up with the emerging preference for such project delivery systems.

 

The choice of a particular style of project delivery system will nearly universally be made by the Owner, driven by factors such as:

 

·       ease of design (buildings vs complex building projects);

·       desire for design flexibility during construction;

·       availability of suitable builders/project managers, and balance sheets of such builders;

·       political considerations;

·       budget constraints vs performance of completed project.

 

On major public sector projects, the use of standard form fixed-price contracts would be more prevalent than  on similar scale private sector projects (though, in contrast, BOT projects are essentially public sector projects delivered by the private sector).

 

1.                       Fixed Price Contracts

The traditional form of construction contract has been a fixed price contract.

The general operation of this type of contract requires the Builder to tender on, and then take the risk in relation to, the price of the works. The Builder, irrespective of the actual cost of the works, will be entitled to be paid no more than and no less than the Contract Sum, as agreed between the parties prior to commencing the works.

In fact, for a number of reasons which are discussed elsewhere in this and related topics, a fixed price contract is rarely performed for exactly the amount of the originally agreed Contract Sum.  For example, if the Owner delays the Builder in obtaining the site, the contract would usually provide for an increase in the Contract Sum.

The critical characteristic, however, of a fixed price contract, is that the Builder takes the risk as to the ultimate price, and that the parties agree to pay the Contract Sum (as adjusted pursuant to the provisions of the Contract).

2.                       Cost Plus

The critical characteristic of the cost plus contract is that there is no risk, as to cost, borne by the Builder. 

The Builder and the Owner agree, at the time entering into the Contract, that the Builder will perform the works, and that the Owner will pay for those works, on the basis of the actual cost of the Works to the Builder, plus an agreed fee, usually an agreed percentage of that sum (or some other agreed incentive over and above the actual cost of the works).

A cost plus contract is, therefore, risk-free, as to cost, for the Builder. 

This does not mean, however, that the Contractor is entitled to charge whatever he likes.  The Contract will usually provide that the Builder has to verify and/or justify the cost of the works to be charged under the Contract.  Further, one could envisage circumstances where, through negligence by the Builder or some other reason, the Builder would not be entitled to recover the full cost of those works.

There are flexibility reasons why such an arrangement may be attractive from time to time for a Owner. 

For example, the Owner might have a strict budget to comply with, and may be in a position of being able to increase or reduce the Works as they are performed (for example, by deleting or adding parts of the Works, or by increasing or decreasing the quality of the selected materials) to ensure that the final cost of the Works remains within that strict budget.  (In theory, this should be equally possible under a fixed-price contract.  For the reasons referred to above, however, in certain instances the Contract Sum being able to be adjusted, a Cost Plus Contract, where the Works themselves are able to be changed during construction, might, conceivably, provide a more convenient method of ensuring that the cost stage within particular limits, albeit that the Works to be performed may change from that which was originally proposed.)

The nature of cost-plus contracting, therefore, is that the Builder agrees to perform the works but that the risk as to the final cost of those works is borne by the Owner, not the Builder (the reverse of the position under the fixed price contract).

3.                       Design & Construct Contract

A design & construct contract requires the Builder to tender on the works described in the Design Brief (prepared by the Owner), and tender not only for the construction of the works described in that Design Brief, but also for the completion of the detailed design, consistent with that Design Brief.

There are a number of construction reasons which suggest that the design & construct method of contracting has the potential to reduce the overall cost of construction to the Owner. 

The nature of this type of contract is such that the Owner is able to enjoy the advantages of design efficiencies which Builders, through their contracting experience, may be able to incorporate into the design of the works, which may have the effect of reducing construction cost (this is discussed further below).

The Owner is still required to adequately specify (in the Design Brief) the works to be completed for the Contract Sum.  The degree to which that work is specified, however, is less than that which would occur under a construction only contract.  The accuracy of the Design Brief (which, again, is discussed further below), is critical to the Owner being able to rely on the design & construct contract.

4.                       Project Management Agreement

A project management agreement is one in which the Owner contracts, not with a Builder who would perform the construction (or the design and construction) works, but with a person who would manage the project on behalf of the Owner, whether by performing the works in part or wholly himself, or by contracting out part or all of the works on behalf of the Owner, or a combination of all of the above.

There is an infinite variety of possible project management contract types (these are discussed further below). 

The nature of a project management agreement, however, is that the Owner engages a person to manage the project on its behalf, rather than engaging a Builder to construct the Works. The functions typically performed by a Project Manager, therefore, are usually more extensive than those which might be performed by a Builder.  Further, the risks borne by a project manager, under a project management agreement, are typically less than, or at least different to, those borne by a Builder.

The types of functions performed by a project manager, pursuant to a project management agreement, typically include the design, or procurement of the design on behalf of the Owner, the construction or procurement of the construction on behalf of the Owner, and, in particular instances, other activities including, for example, site selection, site acquisition, permit approvals, advertising of the project, leasing or pre-leasing of the project, and/or other activities which might otherwise need to be performed by the Owner.

The essential feature of the project management agreement is that the works to be performed pursuant to the agreement are the necessary management services rather than the contract construction works.

5.                       Construction Management Agreement

A construction management agreement is similar in most respects to a project management agreement, except that, typically, the services to be provided by the Construction Manager are restricted to construction activities only (rather than, for example, design activities, site acquisition, leasing activities...).

Accordingly, construction management agreements are, typically, similar in structure to project management agreements. 

The substantive functions to be performed by construction management, typically, include engaging trade builders on behalf of the Owner, and potentially, the provision of preliminaries for those trade builders.

The functions performed by the construction manager might include any or all of the functions set out in Schedule A[1].


6.                       Managing Builder Contract

The Managing Builder might be characterised as a hybrid of a project management/cost-plus/fixed price contract. 

Typically the features of such a contract would include:-

* the Managing Builder contracts with the Owner to manage the construction of the works on behalf of the Owner;

*the Managing Builder contracts with the Owner to provide, at a fixed price, or alternatively at a percentage of the total contract price, certain aspects of the works (for example, the preliminaries, including crane hire, site sheds, supervision services...);

*the Managing Builder may perform all or part of the design services for the Owner;

* the Managing Builder will arrange the trade packages, tender and enter into the trade contracts on behalf of the Owner and, potentially, itself perform some of the trade contract works;

* the Managing Builder will perform the usual supervision, reporting activities required on the project to keep the Owner informed of the progress of the works.

The attraction of the Managing Builder type of contract is its flexibility and the skills which the Managing Builder may be able to bring to bear in the procuring the Works, to assist the Owner.

7.                       Warranted Maximum Price Contract

A Warranted Maximum Price Contract is, in substance, a cost-plus contract between the Owner and the Builder, which, in turn, is subject to an upper limit (the Warranted Maximum Price), above which, subject to certain conditions, some of which are discussed below, the Builder will bear the risk as to costs.

Under a Warranted Maximum Price contract, the Builder is to be paid on a cost-plus basis up to a certain limit.  Over and above that limit, the Builder is not entitled to any further payment.  That limit, however, as in the case of the Contract Sum under a Fixed Price Contract, is subject to adjustment in certain circumstances (for example, where the Owner varies the works, or where the Owner causes delay and/or additional cost to the Builder).

The benefit of the Warranted Maximum Price contract is in giving some upper limit degree of comfort as to the total cost of works, provided those works are adequately  described as to scope, yet allow the parties to enter into the contract on a cost-plus basis where that is an appropriate vehicle for them (this is discussed further below in paragraph 2.3.2).

8.                       Build Own Operate Transfer (BOOT) Project

In recent years, in Australia, there have been a substantial number of major construction projects which have been performed using the BOOT, or BOT vehicle.

The basic structure of a BOOT project is that the Builder agrees with the Owner not only to build the project but to arrange finance for the project, and then, using that finance, to build the project, to own the project for a limited period, to operate the project throughout that period, and then, at the end of that period, to transfer the project to the Owner.

Typically, this style of structure is employed on public infrastructure projects where, but for the intervention of private sector financing, the project might not proceed.


1.2                 STANDARD FORMS

 

 

There are a number of standard form Conditions of Contract generally in use in Australia, particularly within the public sector. Those standard forms include:

 

                                  AS2124/AS4000

                                  JCC

                                  NPWC3-1981

                                  PropCon 1

 

AS2124/AS4000

 

AS2124 is the Standards Association of Australia produced General Conditions of Contract for construction projects.

 

The document was first published in 1952 and was then known as CA24.  Since that time it has been reproduced in several editions, changing its designation in 1978 to AS2124.  AS2124 was revised in 1978, 1981, 1986 and 1992.

 

The Standards Association of Australia has, in recent years at least, hoped to encourage universal use of AS2124 on building projects.  In particular, in the 1986 revision, and again in the 1992 revision, SAA hoped to discourage the use of the alternative NPWC3‑1981 General Conditions of Contract by the public sector in favour of AS2124.  (In the 1986 revision, therefore, many of the features of NPWC3‑1981 were incorporated.)  This hope has only been partially successful, perhaps for some of the reasons suggested below.


There are, however, a number of unfortunate drafting errors in the 1992 revision of the document, attributable no doubt to the committee process of revision, which would need to be remedied before the document is suitable for use on major building projects.

 

 In brief, those drafting flaws include:

 

(i)              The document, in its treatment of Bills of Quantities, places the risk of pricing the works with the Owner rather than the Builder (contrary to the recommendations contained in "No Dispute" which recommended the reverse).

 

(ii)       uncertain risk allocation in a number of important areas (e.g. default of selected Sub‑builders);

 

(iii)       inadequate security/retention provisions, which disentitle the Owner from access to security or retention in the event of defective work removing the commercial equivalence of bank guarantees to cash;

 

(iv)            no provision of collateral contracts within the document (perhaps this is a reflection of the failure of the committee to follow the commercial trends);

 

(v)       complex logical difficulties relating to the conflicting roles of the Superintendent (as between his role as agent for the Owner and as an independent certifier);

 

(vi)            the document does not include an acceleration clause;

 

(vii)           the latent conditions clause is a subjective test likely to favour inexperienced Builders;

 

(viii)          the extension of time clause has a number of logical and commercial difficulties;

 

(ix)            the certificate of progress payments by the Superintendent requires the Superintendent to certify for claims, which may involve a legal judgment, and for claims, which may arise out of his own error, which are likely to result in challenges to the certificate by the Builder;

 

(x)             the dispute resolution clause does not constitute a binding arbitration agreement.

 

It seems that, irrespective of the worthy aims of Standards Association of Australia, the document is certain to be substantially amended by Owners prior to use on major projects, or not used at all.

AS4000 (until recently AS2124) is the Standards Association of Australia produced General Conditions of Contract for construction projects.

 

The document was first published in 1952 and was then known as CA24.  Since that time it has been reproduced in several editions, changing its designation in 1978 to AS2124.  AS2124 was revised in 1978, 1981, 1986 and 1992. AS4000 is the 1997 revision of this standard form.

 

The Standards Association of Australia has, in recent years at least, hoped to encourage universal use of AS4000/AS2124 on building projects.  In particular, in the 1986 revision, and again in the 1992 revision, SAA hoped to discourage the use of the alternative NPWC3‑1981 General Conditions of Contract by the public sector in favour of AS2124.  (In the 1986 revision, therefore, many of the features of NPWC3‑1981 were incorporated.) 

 This document, in both the AS2124-1992 and the AS4000-1995 revision, has drafting problems. Yet still, in my view, it should generally be adopted where possible, particularly on lower value contracts, in the interest of universal use across the country eventually leading to lower tender prices.

 

There will be debate as to the extent to which the latest revision should be adopted in favour of the previous revision.

 

There will also be debate as to the extent to which the latest revision should be amended prior to using that document. I simply add my vote to the use of the AS2124 family, wherever possible, with as little amendment as possible (having regard to the size and complexity of the particular contract). It seems to me that, drafting problems accepted, the universal adoption of this family of contracts will ultimately increase the prospects of lower tender price.

 

                       

JCC

 

The JCC family of contracts was first released in January 1985 in two documents:-

 

JCCA - 1985 Building Works Contract (with quantities)

 

JCCB - 1985 Building Works Contract (without quantities)

 

The document was prepared jointly by the Royal Australian Institute of Architects, the Master Builders Federation of Australia, and the Property Council of Australia (then BOMA).  It effectively replaced the previous standard form conditions of contract which were in common use, the RAIA Edition 5b-1970 Conditions of Contract.

 

The contract was prepared by a committee comprised of representatives of those three organizations, hence the title JCC (Joint Contracts Committee).  Recently the Joint Contracts Committee released two new versions of the document:-

 

JCCC - 1993 Building Works Contract (with quantities)

 

JCCD - 1993 Building Works Contract (without quantities)

 

Those editions were released in March 1993 and represent the present state of the JCC contract.

 

The JCC document, it may be fair to say, has, at least until recently when there have been a number of new options, become the most commonly used form of Conditions of Contract amongst the various standard form conditions available.

 

There may be, on some views, some difficulties with the document, however nothing which could not be remedied easily.  Perhaps the following comments might be made of the JCC family of documents:-

 

(i)              the latent conditions clause might reasonably be limited to "material" and/or "substantial" differences in conditions, and could be amended to impose a positive obligation on the Builder to investigate the site and draw its own conclusions as to the site conditions likely to be encountered;

 

(ii)             the document, no doubt in the interest of risk/sharing in the hope of a more even contractual approach, introduces an option, in the Appendix, for the parties to insert a percentage of delay costs to be paid to the Builder in respect of a number of delays not attributable to the Proprietor (the better view, for Proprietors, might be that the Builder is only to be entitled to delay costs where a delay is caused by the Proprietor);

 

(iii)       clause 12.09 is, in the view of some commentators, at best meaningless, and at worst, provides an unnecessary and illogical tactical advantage to both parties (but more so, it seems to me, to the Builder);

 

(iv)            the contract provides an arbitration clause which, even if arbitration is to be preferred, is unnecessarily procedurally complex.

 

Having said this, the document has many excellent features, in particular, a clear designation of the role of the Architect, on the one hand when acting as agent of the Proprietor, and on the other when acting as independent assessor.  Further, it has the added attraction of being widely in use.  Accordingly, this is a well understood standard form.

 

The recent editions have expanded the insurance clauses. 

 

On balance, JCC remains a viable and popular option.

 

 

 

1.3